How to build a vacation home for two week
The author has decided to build a country house, which first planned as a summer cottage accommodation and temporary winter visits. Basically he built his father, without the use of cheap labor of non-Slavic appearance. Under the cut you will see the whole process of construction of this extraordinary adventure lodge, which was built to remind just two weeks.
Well, let's start: the foundation pile, top filled "coppers."
First Day
Ready harness, begin to lay temporal overlap. End of day - time to put together and put the first wall.
Day Two: Collect and raise the walls, everything is pretty easy and simple, there are drawings (he produced) on the board and chop them lying cobble together a wall, then set, securing temporary struts
This is the result of the second day
Day Three:

The ends do with gables, for discerning - System "Balun". To be able to move "on the second floor" collect overlap and throws a few boards.

Rafters on the second front is not time to put - no strength. At the end of the day:
Fourth: Put the rafters along the entire length, as you can see the weather began to deteriorate and if the first three days I worked in a shirt, then all of posledeyuschie hoodies did not get out - August in St. Petersburg unpredictable.
End of the day: Already want only one thing: to fall and fall asleep :)
Fifth: Pulled membrane began to cover a roof ONDULIN, the law of meanness rose to a gale and the house is not claimed - had to quickly sew up the gable wall and part of the second part of OSB roof and do not close.
End of the day:
Sixth: close the roof, two walls stitched bottom, even the strength to photograph no longer exists. The house is covered - you can breathe a little, go to the city to wash, to buy food and just lie down :)
End of the day:
One day of rest, rebounded slightly and again in battle. seventh day:
Insulate, top closure membrane until the stapler, then all stuffed rack bars. Of course it started to rain ...
End of the day: ready two walls.
Eighth:
The third and fourth walls ready.
Ninth:
Brought and put windows, this time I sewed four hours one wall siding. While taking a job as altered until dopenivali - the time has gone, the end of the day it succeeded:
Tenth:
Sewed both gable, the more - the faster it turns out to work, the last blank wall sewed all for a cheap Chinese polchasa.Votknul door. Here is the view from the other side:
Eleventh: Digging a grave for septic tank
Client shipped, just bury the supply pipe to the desired slope
Twelfth:
Insulate and bury

All the house is closed, buried septic tank, the season is over. wintering Picture: